The College of New Jersey

Apply     Visit     Give     |     Alumni     Parents     Offices     TCNJ Today     

Current Projects

Construction Website Update as of July 31, 2020

If there are any questions or concerns regarding any of these projects, please contact Campus Construction at 609-771-3234, or email jamest@tcnj.edu.

Travers and Wolfe Elevator Replacements: Complete and in close out.

Heat Recover Steam Generator: work is progressing on schedule for a fall start up.

Lacrosse field turf replacement: the existing turf has been removed only to find the
existing e-layer and subsurface stone base needs to be replaced. Bidding for this portion
of the project is happening now, and hopes are we can still have the project completed
this fall.

Kendall Hall and Mayo Hall Dimmers: substantially completed, in close out.

Parking Garage repairs: substantially completed and in close out.

Domestic Water Pipe replacements: early phases are completed, the project continues
throughout the fall.

Centennial A/C Rooms: work is underway and is expected to be completed in August

Feeder A Replacement: bidding is completed. Excavation work will take place this fall
and cable replacement over winter break.

Fire alarm replacement campus wide: the entire campus fire alarm system is going to
be replaced starting this year and taking 2 years to complete. Fiber cabling will be
installed throughout the campus, and all panels will be replaced. Bidding is completed
and the process will begin this fall.

Packer Pool Re-grouting: contractor is on site and the work is being expedited to be
completed by mid-August.

New Res. Hall HVAC cleaning: all room units are being cleaned and remedial work is taking place prior to students arrivals.

 

See potential disruptive construction activities on campus.View Map (PDF)
+